Background information and customer requirements
Longi Green Energy Xianyang Branch's Wastewater Treatment Plant Project
The sewage treatment plant mainly serves the production wastewater of Longi Green Energy Xianyang Branch's annual production of 15GW high-efficiency single crystal battery project and other industrial enterprise drainage. The total design capacity is 60000 tons/day, of which the drainage of Xianyang Branch of Longi Green Energy is 45000 m3/d, accounting for 75% of the total water volume.
Solution
TAfter on-site investigation and in-depth technical exchange with the design institute and the technical personnel of China 17th Metallurgical Group Co., Ltd., the sewage treatment plant in Jinghe New Town Industrial Ghetto, Jingyang County, Xianyang, Shanxi Province has determined to adopt three sets of 40kg/h ozone systems of Guolin ozone process.